Severn Trent works update July 2026
Severn Trent continue works in the Parish and will be spending approx 4 weeks in Lapley. During this period there will be road closures, residents and emergency vehicles will always have access.
The liaison officer dealing with our parish us Mital Vaghela and she is happy to answer queries direct. Her contact details are [email protected] contact number 07974 429872
Please see the attached letters outlining planned works and the below information:
There are currently three teams working in the area.
1. Wheaton Aston Pipelines – Cul-de-sac Works
Letters have been sent to all residents and businesses affected by these works.
2. Bickford Close
Works commenced on 29 June and are scheduled to last for four weeks.
Text messages have been sent to all residents living within the cul-de-sac.
3. Wheaton Aston – Lapley Phase 6
Works are due to commence on 1 July and are expected to continue for 12 weeks. The road will be closed in sections as the work progresses along the stretch, rather than being closed in its entirety at once. A diversion route will be in place throughout the duration of the works.
Please note that if emergency vehicles require access, or if there are any large deliveries, we will accommodate these requests as quickly as possible.
Update on the water pipe replacement in Wheaton Ashton
As part of a major replumbing to the water network across our Central region, we’re replacing old water pipes in Wheaton Ashton This essential work is part of our huge investment in the Midlands to reduce the risk of leaks and bursts, improve reliability, and ensure your water supply stays strong for generations to come.
You may have seen our team in the area replacing the water pipes as part of this major upgrade. The team have been on site since March 2026 and have replaced 1003m of pipe.
We are now ready to move to the next phase of works.
Where and when we’ll be working
The team will be working from Wednesday 1st July, from Lapley to Church Eaton, Stretton Road, Wenlock Bank and Church Lane for approximately 12 weeks.
During this period, road closures will be in operation – access will be maintained for residents who live within the closures.
We know our work can be disruptive and we’re sorry for any inconvenience this essential work may cause. Please be assured that we will do everything we can to minimise any inconvenience and complete the work as quickly and safely as possible.
As part of a major replumbing to the water network across our Central region, we’re replacing old water pipes in Wheaton Ashton This essential work is part of our huge investment in the Midlands to reduce the risk of leaks and bursts, improve reliability, and ensure your water supply stays strong for generations to come.
You may have seen our team in the area replacing the water pipes as part of this major upgrade. The team have been on site since March and we are now ready to move to the next phase of works
Where and when we’ll be working
The team will be working from Monday 13th July until Sunday 30th August, beginning on Beech Close. During this period, there will be road closures and restricted access covering all of the cul-de-sac. Access will be maintained for residents who live within the closures.
The provisional schedule of works will can be seen below:
Phase Road Name Start Date* Approx Duration* Traffic Management
1 Beech Close 13/07/2026 2 Weeks R/C With restricted Access
2 Oak Drive 20/07/2026 2 Weeks R/C With restricted Access
3 Badgers End 27/07/2026 2 Weeks R/C With restricted Access
4 Cranbrooks 03/08/2026 2 Weeks R/C With restricted Access
5 Oaksmoor Close 10/08/2026 3 Weeks R/C With restricted Access
We know our work can be disruptive and we’re sorry for any inconvenience this essential work may cause. Please be assured that we will do everything we can to minimise any inconvenience and complete the work as quickly and safely as possible.
Stay up to date
We will do our best to stick to the start and end dates outlined above – however, due to circumstances beyond our control, sometimes these do change. We will of course keep you up to date with any alterations.
To ensure you stay updated, please make sure your contact details (phone, email, address) are accurate, download the NextDoor app and keep an eye on local social media channels. You can also visit our website at stwater.co.uk/mains-renewal.
Will my water supply be affected?
If we plan to interrupt your water supply, we’ll notify you in advance with a card posted through your door letting you know the date, earliest start time and the latest end time that your water will be interrupted. We’ll be doing our best to make sure your water supply is unaffected for the duration of our work.
During or after the work, there’s a small chance your water may appear discoloured. This is nothing to worry about and will quickly go back to normal. We’ll be doing our best to make sure your water supply is unaffected for the duration of our work. To find out more about clearing discoloured tap water, please visit our website www.stwater.co.uk/discolouration.
Smartening up your water supply
While we’re carrying out this work, we’ll also be fitting smart meters within your area. These clever devices put you in control by showing exactly how much water you use and alerting you if there’s a leak.
Did you know that switching to a measured bill could save you money? In fact, 3 out of 5 Severn Trent customers could be saving right now.
👉To switch your bill, follow this URL: stwater.co.uk/switchmains
👉 To find out more about smart metering, follow this URL: stwater.co.uk/smartmains
Business owners
If you own or operate a business that receives visiting customers who purchase goods or services from you and our works are affecting your sales income, please contact our Business Loss Team
at [email protected] for further advice.
Who do I contact about the work?
• If you have any queries about this work, please speak to a member of the team on site who will help in any way they can or get in touch with me on 07974429872 between 08:00am – 16:00pm.
• Visit our Planned Improvements website at stwater.co.uk/planned-improvements.
• If you experience any issues with your water or sewerage service while the work is being done, please call our 24-hr operations centre on 0800 783 4444.